Media Library

Media Library & Case Studies

Taloona Sewage Treatment Plant

Customer: Origin Energy - Australia Pacific LNG

Completion Date: 1/11/2012

Location: Spring Gully, QLD

Specifications & Features:

Water Use: Dowdens Pumping and Water Treatment to design, manufacture, supply, install and commission a Rotating Biological Contactor Sewage Treatment Plant to be utilised at a 60m3/day 200 man work camp; and supply and install 4 hectares of pop-up sprinklers on site.

Water Quality Requirements: Class B water with additional nutrient removal.

Daily Treated Water Production: 60m3


Details:

Plant Description:

  • System is capable of treating 60m3/day of raw sewage into to Class B effluent
  • 12.2m3 pump station complete with duty stand-by maceration pumps
  • Emergency peak flow storage of 30m3
  • Primary tank, RBC, clarification, chlorine contact tank, treated effluent tanks
  • Control panel housed in a containerised control room
  • Fully automated irrigation of treated water
  • 135m3 capacity wet weather storage tanks installed

 