Sewage Pump System Upgrade

Customer: Sheraton Grand Mirage Resort Port Douglas

Location: Port Douglas, QLD

Specifications & Features:

Sheraton Mirage Port Douglas Resort

Dowdens Pumping & Water Treatment's Proserpine branch provide a range of products and services to island resorts throughout the Whitsundays and Northern Queensland; supplying and servicing everything from pool pumps to major sewage treatment / pumping stations and irrigation systems. We pride ourselves on being able to provide a large range of products across all facets of resort infrastructure.

Dowdens Pumping & Water Treatment's Proserpine branch regularly service customers across local off shore resorts, as well as working extensively with mainland tourist attractions and resorts for both sales and servicing. With extensive knowledge and experience in this area we are confident that our team of experts can provide solutions to clients problems. Dowdens Pumping carries a large range of spare parts and our service team are proud to provide comprehensive and professional after-sales service.

Recently Dowdens Proserpine were engaged by Fullshare Holdings (owner / operators of the Sheraton Grand Mirage Resort Port Douglas) to upgrade 5 existing onsite pump stations that had reached the end of their service life. At the projects inception Dowdens Proserpine conducted a thorough audit of the onsite pumping systems - the subsequent detailed report submitted to Fullshare Holdings resulted in Dowdens being awarded the contract to replace the ageing sewage pump stations. Dowdens Proserpine then set about designing a more efficient and reliable sewerage pump system that was to include smaller and more energy efficient Grundfos pumps, resulting in a reduction in the required maintenance and considerably lower overall energy use onsite. Dowdens Pumping & Water Treatment are Authorised Grundfos Dealers throughout the Whitsundays / Mackay / Rockhampton regions.

"Fullshare (owners of Sheraton Grand Mirage Resort & Mirage Country Club) recently engaged Dowdens Pumping & Water Treatment's Proserpine branch to carry out an on-site audit & submit a report on the condition & performance of our 30 year old sewage pump stations. This audit & subsequent detailed report was thorough & included recommended actions, therefore allowing Fullshare to be fully informed on the condition & improvements required to improve the condition & performance of these important components of our asset. Following a Tender process, we engaged Dowdens Pumping & Water Treatment to carry out the recommended upgrade works to the sewage pump stations.

The challenges of the project were met well by Dowdens Pumping & Water Treatment under the management & extensive office / site based efforts of Kevin Krog (Dowdens Proserpine branch) & his industrial workshop team. Such challenges faced were a fully operational Resort & Country Club, difficult access to some stations, 30 year old supporting infrastructure & services including power supplies as well as contending with it being the wettest & most humid time of the tropical year. Kevin was also excellent at assisting us to liase with the Douglas Shire Council for these works. We will continue to utilise Dowdens Pumping & Water Treatment's expertise & personnel at this property when the need arises & would thoroughly recommend them for these types of works."

Scott Conners
Senior Projects & Assets Manager
Sheraton Grand Mirage Resort Port Douglas

Fullshare Holdings (Sheraton Mirage Port Douglas Resort) Sewage Pump Stations Upgrade


Fullshare Holdings (Sheraton Mirage Port Douglas Resort) Sewage Pump Stations Upgrade

Details:

Fullshare Holdings - Sheraton Mirage Port Douglas Resort

Once the design was accepted Dowdens began works that would see 10 new Grundfos sewerage pumps being installed in 5 existing pump stations. The projects scope included supplying and fitting all rails, brackets, lifting chains, concrete pump station lids and non-return valves. Together with the design and installation of Grundfos electronic control panels (Grundfos CU362 Waste Water Controllers) & remote monitoring systems (Grundfos Remote Management [GRM]) which allows for SMS & Email to be sent to relevant site operators alerting them to any faults. The GRM system also allows for system alarms to be reset and pump duties to be modified remotely via any smart-phone or PC. Full product and system descriptions can be viewed below.

The aim of this project was to provide a modern and efficient sewerage pumping system that was energy efficient, reliable, had improved remote monitoring capability and increased level of safety for Dowdens Servicing and onsite technicians. The Dowdens Infield Service Crew began by removing the existing 30-year-old pumps, rails, brackets, lifting chains, heavy concrete lids and control panels. These were replaced with more efficient and reliable Grundfos pumping and monitoring equipment. During installation and commissioning Dowdens had to schedule works to meet the resorts strict operation requirements, ensuring the project proceeded with little to no impact on the resort guests.

The existing concrete lids were damaged and unsafe and needed to be replaced. Dowdens provided 'light lift' aluminium lids with integrated safety grates (pictured below) to minimise the risk of falling into the wet well whilst servicing the pumps. 3 out of the 5 existing control panels were deemed unsafe by Dowdens Electricians and required replacement with new stainless steel panels incorporating the Grundfos CU362 Pump Controllers and Grundfos Variable Frequency Drives on the 2 main pump stations. Dowdens also provided Sheraton Grand Mirage Resort Port Douglas with scheduled servicing of the Grundfos SEV & SE1 pumps; Grundfos CU362 Waste Water Controllers; Grundfos Remote Management [GRM] Systems; Dowdens custom built aluminium lids with safety grates; Stainless steel pump rails; 800kg rated lifting chains & the Backflow protection on wash down taps. The entire project was delivered on time and within budget.

Dowdens Pumping & Water Treatment design philosophy for this project was: Cost Effectiveness - Current Best Practice - Ease of Installation - Simple & Effective Plant Operation - Pump Station Reliability - Advanced Remote Management Capabilities - Reduced Ongoing Maintenance.

Sheraton Grand Mirage Resort (Port Douglas) - Sewage Pump Stations Key Components:

Fullshare Holdings (Sheraton Mirage Port Douglas Resort) Sewage Pump Stations Upgrade

 